Antara Living Lot 2 Construction Updates - November 2022

Updated: Jul 20, 2023


SUMMARY OF CURRENT ACTIVITIES UNDERWAY ON SITE OR COMPLETE IN THIS PERIOD

  • FRP of Capping Beam to Western and Northern Elevation – 100%

  • Drilling and Piering of Piles to Western and Northern Elevation – 100%

  • Shotcrete 1st Drop to Western and Northern Elevation = 75%

  • Bulk Excavation to Basement 1 Level – 75%

  • Temporary Anchoring to the Western and Northern Elevation [Drop 1] = 75%

  • Inclinometer Baseline Reading – 100%

  • Capping Beam Baseline Survey Readings – 100%