Antara Living Lot 2 Construction Updates - October 2022

Writer's picture: Heming QuanHeming Quan

Updated: Jul 20, 2023


For the month of October 2022, we have been delayed 8 days from inclement weather which has impacted progression of the removal of GSW and classification of the site. Chalouhi has also completed and classified half of the site for the removal of the GSW ready for the piling to commence next week. Demolition and clearance of the hot spot has also been completed in the month of October.

Design has progressed in the month of October with the Wall type drawings, Concrete Set-out Plans, Façade design, Structure Design and Civil Design have been issued for IFC. With final coordination of the services design up to level 7 been issued to the ICA, PTW and Lucid for their review and comments.


SUMMARY OF CURRENT ACTIVITIES UNDERWAY ON SITE OR COMPLETE IN THIS PERIOD

  • Completed Semi-permanent fencing, pedestrian and vehicular gates access gate

  • Completed Services boring under road between no’s 2 and 1 Murray Rose Ave

  • Completed Tree removal on site in buffer zone along Bennelong Parkway and between parking spaces on Murray Rose Ave

  • Completed Demolition and site clearance

  • Remediation of Hotspot

  • Established Piling Rig

  • Excavated Zone 1 Capping Beam

  • Removal of and testing of GSW

  • Connected power and water to site

  • Connected water to site sheds