The project site establishment works have only just commenced on site with no issues to date which is a little later than programme for various reasons.
Whilst Construction Certertificate Issue is running behind Program, this is not affecting progress of the works on site with overall design and procurement for the project progressing well.
SUMMARY OF CURRENT ACTIVITIES UNDERWAY ON SITE
Site establishment underway
Semi-permanent fencing, pedestrian and vehicular gates access arrangements presently being completed
Installation of banner mesh and site signage
Site sheds landed on no. 1 Murray Rose Ave
Services boring under road between no’s 2 and 1 Murray Rose Ave
Tree removal on site in buffer zone along Bennelong Parkway and between parking spaces on Murray Rose Ave
Paving removal in excavation areas
Demolition, excavation and form/reo/pour cross overs at no’s 1 and 2 Murray Rose Ave
Establishment survey set out of benchmark and gridlines